single machine scheduling problem gotz1408 03/02/07
    I cannot find a way to model the following problem, maybe one of you guys can help me:

    Consider the following machine scheduling problem: n jobs, denoted by 1,...,n, need to be scheduled on a single machine. The machine can process at most one job at a time and it is not allowed to preempt a job, i.e., as soon as a job has been started, the machine must process this job until completion. The processing time, that is, the time it takes to fully process a job, is Pj (j=1,...,n).
    The goal is to minimize the sum of completion time,i.e., let Cj denote the completion time of job j (in a given schedule).
    The fact that the machine can only process one job at a time and is not allowed to preempt jobs, implies that either job j has to start after job k has finished or the other way around.
    Formulate the above problem as an integer (linear) program, using the decision variables Cj. (You might need some additional variables.)

    Please, help me...

Summary of Answers Received Answered On Answered By Average Rating
1. If I understand the problem correctly, the sum of completion...
03/02/07 Jim.McGinnessNo rating received!
Your Options
    Additional Options are only visible when you login! !

vq/Li   © Copyright 2002-2008 Answerway.org. All rights reserved. User Guidelines. Expert Guidelines.
Privacy Policy. Terms of Use.   Make Us Your Homepage
. Bookmark Answerway.